2008 ARTICLES ABOUT INDIAN POINT

Here are 2008 Indian Point articles, editorials, op-eds and letters in chronological order with the most recent first. You can also find news from 2007, 2006, 2005, 2004, 2003, 2002 and 2001. If you find an article that should be included, please call us at 1-888-474-8848.

Pieces specifically about the ongoing leak of tritium and strontium 90 can be found here.

December 27, 2008

Nuke site needs go beyond sirens

Editorial
POUGHKEEPSIE JOURNAL

After nearly two years, the Indian Point nuclear power plant in Buchanan has all but satisfied federal regulators that the facility's updated siren system can perform as a primary warning system. It's about time. But there are larger issues about the plant's operation that must be addressed.

The siren system will give four counties - Westchester, Rockland, Putnam and Orange - a new emergency alert it can adapt as technology evolves. But the long path to this point is another reason the Nuclear Regulatory Commission must retool its requirements for extending licenses of nuclear power facilities, especially in this case.

Entergy Nuclear, which owns the plant, missed three deadlines in 2007 to install the system, and rushed to avoid missing another. The company was fined $780,000 as a result, and the budget for the siren system increased from $10 million to well more than $15 million. During recent full-volume testing, only one of 172 new sirens failed to operate properly. That was the third time the system had surpassed the minimum standard set by the NRC.

Several municipalities in the densely populated vicinity of the plant have passed resolutions demanding the plant be shut. While that would be ideal, the power generator from the plant wouldn't be easy to replace at this point. The region's congressional delegation has been pushing for at least an independent safety assessment of the plant before permits are renewed, and municipal officials in Westchester and nearby New Jersey launched a court battle over the issue of evacuation of the area around the plant.

Litany of problems

Indian Point has had a host of other problems, ranging from leaks of radioactive water that have had to be contained, to the failing warning signals and a shoddy evacuation plan. The licenses for the two reactors at Indian Point expire in 2013 and 2015, and Entergy wants to extend those by another 20 years.

The population density and the ability to successfully evacuate during an emergency are not examined in a 20-year license renewal, but they should be. Only issues such as managing aging pipes and other infrastructure or possible environmental impacts are considered in relicensing. That is not good enough.

The NRC is finishing up its review of the siren system and is expected to issue its final report by January. The relicensing procedure continues and promises to be contentious all the way through.

The problems Indian Point encountered with its new siren system back up the public pleas that the relicensing process must be made more rigorous.

Given the serious nature of the material involved and the plant's proximity to millions of people, the highest standards should be used in determining Indian Point's future.

http://www.poughkeepsiejournal.com/article/20081227/OPINION01/812270305/1004/opinion  

###

December 15, 2008

Can Nuclear Power Compete?

Newly approved reactor designs could reduce global warming and fossil-fuel dependence, but utilities are grappling with whether better nukes make market sense

By Matthew L. Wald
SciAm Earth 3.0

On an August afternoon in Washington, D.C., typically miserable for its heat, humidity and stillness, reporters gathered at a downtown hotel not known for its air-conditioning. Stuffed inside a windowless conference room that was being heated still further by the television people’s lights, we waited for Michael J. Wallace, who had been trying, in fits and starts, to unveil nuclear power’s second act.

On arrival, Wallace, a meticulous manager not known for ad-libbing, looked out over the sweating reporters and smiled. “It’s days like today that highlight the real need for new, emissions-free, baseload power,” he said. Unless we get started soon, he added, rolling blackouts could become the norm.

Wearing a suit and tie and seeming to enjoy the heat, Wallace announced that his company, UniStar Nuclear Energy, a partnership between Constellation Energy and the European nuclear consortium Areva, was looking to build a new kind of nuclear power plant in the U.S. and elsewhere. “I’m pleased to say I played a role in the last round of nuclear power plant development, and I’m really pleased to be involved,” the chairman said, calling to mind a graying astronaut who walked on the moon years ago and now wanted to do it again.

That was in 2006. Since then, Wallace has intermittently made new announcements about incremental progress toward building a new reactor about 45 miles south of Washington, which could be the first U.S. nuclear plant put on order and built since 1973. Wallace’s original feat was leading the start-up of two of the nation’s last big nuclear plants, completed in 1987 in Illinois. Like another moon shot, the launch of new reactors after a 35-year hiatus in orders is certainly possible, though not a sure bet. It would be easier this time, the experts say, because of technological progress over the intervening decades. But as with a project as large as a moon landing, there is another question: Would it be worthwhile?

A variety of companies, including Wallace’s, say the answer may be yes. Manufacturers have submitted new designs to the Nuclear Regulatory Commission’s safety engineers, and that agency has already approved some as ready for construction, if they are built on a previously approved site. Utilities, reactor manufacturers and architecture/engineering firms have formed partnerships to build plants, pending final approvals. Swarms of students are enrolling in college-level nuclear engineering programs. And rosy ­projections from industry and government predict a surge in construction.

Modern competitive pressures complicate the matter, however. For one thing, in much of the country any new construction would be by “merchant generators”—independent companies rather than large, monolithic utilities. Nuclear power was simpler two decades ago, because utilities built their own plants and could usually pass costs through to captive consumers no matter how big the overruns. But in states such as Texas, Maryland and New York, where the public service commission has separated the generation of electricity from power transmission and distribution, there is no longer a cushion for a generation company that guesses wrong. Such plants must sell electricity at whatever price the market will bear.

That number is hard to predict, because although reactors would exploit current technologies and techniques, so will modern coal and natural gas plants. Gas, especially, has much lower up-front costs, a big consideration if credit remains tight. And gas plants can be built in small units in only three or four years, as compared with six or eight for mammoth reactors.

For nuclear power, the modernization is intended to produce dramatic differences: plants that will run more than 90 percent of the hours in a year and last for 60 years or longer. The ones in service today ran only about 60 percent of the time when they were new and were assumed to have only a 40-year life. But utilities are already signing long-term contracts for large solar generators, and wind turbines are being erected at an unprecedented rate. Those alternatives operate fewer hours of the year, but with no burden of fuel cost or fuel-disposal problems the price of power they produce could be low enough to squeeze nuclear power out of the mix.

Perhaps even more of a question is the shape of the market that reactors would serve. Some states have a goal of zero electric growth, achieved by replacing lamps, pumps, blowers and everything else that runs on electricity with updated equipment that does the same work with less energy. If growth stopped—an ambitious prospect—new plants would still be needed to replace old ones as they wore out, but far fewer orders would result.

By almost all accounts, cutting demand is a lot cheaper than building capacity. Dan W. Reicher, a former assistant secretary of energy for conservation and renewables, has complained repeatedly that companies will invest in solar plants that produce electricity at 20 or 30 cents per kilowatt-hour, while ignoring fixes that would save comparable energy at a cost of four cents per kilowatt-hour.

Wild cards add even more uncertainty to how much power will be needed. Proponents talk about tens of millions of plug-in hybrid or even electric cars, each of which might use 10 kilowatt-hours a day from the grid to cover 30 or 40 miles of travel. That would substantially bump up demand, but the success of such vehicles is difficult to predict. If millions of the cars did sell, they would mostly recharge at night, which would change the shape of the “load curve”—instead of households consuming peak amounts of power during the day and far less at night, consumption would be at a more constant level across a 24-hour period, which favors technologies such as nuclear that are capital-intensive but operate around the clock with low marginal costs. Consequently, any power company planning a big generating station that takes six or eight years to build does so without a clear prediction of what demand will be by the time the plant is finished.

Potential carbon regulation adds even more guesswork. Governments are seriously considering a flat tax on emissions or a cap-and-trade system that would create a de facto surcharge for emissions. Either way, predicting the price is hard: the initial experience in European trading was a wildly unstable market. Still, economists predict such a system would result in a price that averages in the tens of dollars per ton of emissions. A $10 charge per ton would raise the consumer price of electricity by about a penny a kilowatt-hour. A new coal plant typically produces that much electricity for six or seven cents, so an addition of $20 or $30 a ton would create a huge advantage for carbon-free technologies such as nuclear power.

In fits and starts, a nuclear renaissance might actually be under way. Wallace’s vision is for standardized plants, identical right down to “the carpeting and wallpaper,” that could therefore be manufactured and approved for less than reactors of the past, almost all of which were custom-built. Teams of engineers and craft workers would construct the same plant again and again in different locations; just like assembling furniture from kits, practice would make perfect. The idea that mass production—or, at least, serial production—is cheaper than one-of-a-kind products is nearly universally held in the industry. John Krenicki, president and CEO of General Electric’s Energy Infrastructure division, says site-by-site construction will never create a cost-effective solution.

Wallace’s idea seems to be catching on. The first standardized plant is planned as a third unit beside Constellation Energy’s two existing Calvert Cliffs plants, about 45 miles south of Washington. In July, AmerenUE, a big Midwestern utility, also filed a license application for a cookie-cutter unit. More applications are waiting in the wings: one in Pennsylvania, one in upstate New York, one in Idaho and a twin-unit plant in Amarillo, Tex. All would be built by the UniStar joint venture, in partnership with a local utility or generating company. UniStar has not listed precise costs, but in recent briefings Wallace has pointed to other studies of standardized plants that quote “overnight costs” (not counting interest for construction) of $4,000 to $6,000 per kilowatt of capacity. His plants would be in the upper end of that range, he says. An up-to-date coal plant costs about $3,000 a kilowatt, but charges levied on carbon dioxide emissions, or extra equipment to capture the gas instead, could add substantially to that.

The possibility of a series of new reactors is a stunning turnaround for the industry, which bankrupted some of its customers in the 1980s because of huge cost overruns and which looked so bad in the early 1990s that some completed plants were shut down after only a few years of operation. Proponents say that today energy utilities find greater benefit in a technology that puts the financial risk up front, in the construction cost, and has little vulnerability to later swings in the price of fuel, as natural gas does, or to changes in emissions regulations, as coal faces. Consequently, companies around the country are spending tens of millions of dollars to explore their nuclear options, conducting engineering studies and preparing license applications, even if no one has ponied up the billions of dollars that an actual reactor would require. “There’s a huge sense of déjà vu for me personally,” Wallace says.

More Viable Than Clean Coal

To no one’s surprise, cost will loom large in any decision to plan on a reactor. The first installation of UniStar’s standardized model, known as a European Pressurized Reactor, or EPR, is under way in Olkiluoto, Finland. The project is now behind schedule and over budget, after quality-control problems early in the construction period.

Other reasons to be skeptical of nuclear’s price persist as well. Estimates submitted by utilities to regulators in Florida predicted $8,000 per kilowatt of capacity when transmission and loan interest costs are included. The cost of steel, concrete and labor have all risen, and the recent financial crisis may mean higher interest rates for construction loans, although that would affect the building of any kind of power plant.

Whether a reactor would be cost-effective depends on how it compares with other environmentally sound generation options. Coal plants that capture their own carbon emissions are one choice, but the leading demonstration plant that was being built in the U.S., known as FutureGen, has been scrapped. FutureGen, originally planned for Mattoon, Ill., was overseen by a public-private consortium. The coal would have been cooked in a low-oxygen environment, creating a fuel gas made of hydrogen and carbon monoxide. The hydrogen would be burned for electricity and the carbon converted to carbon dioxide and pumped underground. The only emission would have been water vapor. But as the price of materials rose internationally, the plant’s cost went up even more. In early 2008 the U.S. Department of Energy pulled out. That move left China with the leading project, equally uncertain, which it calls GreenGen.

The Energy Department continues low-level work on so-called Gen IV nuclear reactors, fourth-generation technologies that use altered fuels or produce a more manageable waste stream. Other low-carbon coal technologies are being attempted, too. In Pleasant Prairie, Wis., the Electric Power Research Institute and Wisconsin Electric are testing a process that uses an ammonia-based chemical to bind carbon dioxide in a smokestack so it can be sequestered. But the test deals with only a little more than 1 percent of the plant’s emissions.

“We’re maybe 15 or 20 years behind where we should be for burning coal in an environmentally sound manner,” says Marsha H. Smith, president of the National Association of Regulatory Utility Commissioners. The bottom line is that although nuclear energy has obvious drawbacks such as cost and poisonously radioactive waste, it is far better demonstrated than coal with carbon capture.

More Dependable Than Wind or Solar

At the moment, the fastest-growing source of clean energy is wind. The American Wind Energy Association said in September that installations had reached 20,000 megawatts, double the capacity of 2006, with growth driven by generous tax incentives and state renewable energy quotas. But wind plants run far fewer hours of the year than nuclear plants do; 10,000-megawatt wind machines produce the energy equivalent of only two or three big 1,000-megawatt reactors. Because wind is not “dispatchable”—meaning the generators run only when nature allows, not when operators might order them to—the extent to which it can replace around-the-clock technologies such as nuclear is unclear.

Solar is more predictable, and with certain forms of energy storage may even be dispatchable, providing power during cloudy periods or during high-demand hours after sunset. Current solar facilities reflect the sun’s rays off of curved mirrors to heat water or mineral oil, but experimental systems use materials such as molten salt, which could run far hotter and be stored in insulated tanks for hours or days. Other companies are building massive arrays of photovoltaic cells that convert sunlight directly into electricity.

Generally, however, large solar and wind projects—the kind most likely to be cost-effective—are built in deserts or on remote mountaintops or plains, far from population centers that need the power. So transmission lines must be built to connect supply with demand. “You’re talking about immense amounts of transmission,” says John Rowe, chair of Exelon, one of the nation’s largest utilities. “It requires a really huge grid. I don’t see us going that way anytime soon.” Indeed, a recent Energy Department study concluded that wind could meet 20 percent of American needs by 2030 but would require a new transmission system costing $60 billion or more. Nuclear reactors can be located far closer to consumers and would require more modest additions to the existing grid.

Efficiency Could Forestall Reactors

One of the strongest competitors nuclear power faces is energy efficiency. Improvements in efficiency, driven by the need to reduce greenhouse gas emissions, could for many years offset increases in demand from a growing population with higher living standards, forestalling the need for reactors.

In December 2007 consulting firm McKinsey & Company determined that the U.S. could cut its output of global warming gases by more than 11 percent using conservation steps that were better than free: they would pay for themselves and earn a profit. These “negative cost opportunities” would require little or no technology innovation, the report said. And emissions could be cut by another 17 percent with efficiency improvements that had only a moderate cost.

Amory Lovins, a well-known efficiency expert, has long referred to such opportunities as being better than a free lunch, “lunch that someone pays you to eat.” But the steps are often not taken. One reason is that efficiency is usually number 11 on people’s top 10 to-do lists. For example, a high-efficiency air conditioner costs more than a standard model but will earn back the difference, in electricity savings, in a season or two. Yet many purchasers do not care, especially if they are landlords or builders who will never pay the electric bill.

Other steps might minimize convenience, even those that border on slothfulness. Lots of home appliances, for example, continue to draw power when the switch is “off” so that they are always warmed up and can come back to life instantly. Experts sometimes call this constant draw a “vampire load.” Around the house, all those vampires add up, but hardly anybody knows or cares. As Richard D. Duke, an energy expert at the Natural Resources Defense Council, quips, “What consumer, when buying a TiVo, is going to demand that the manufacturer make the standby power consumption a criteria? Nobody.”

Build before Memory Runs Out

Although individual consumer actions can help, major changes in carbon output will likely require better electricity-generation technologies, retiring much of the coal-fired capacity and replacing it with the most cost-effective combination of modern reactors, renewables and even clean coal. Around the country, players in the electricity business—regulated utilities, independent merchant generators, and municipal suppliers—are placing bets on which options will be the winners.

The competition is a bit like a high school track meet, however, in which competitors’ starting lines are staggered around the track. Nuclear has the longest path, because it takes more time to obtain site and building permits and to clear safety reviews. Yet anybody even thinking of a new reactor must pony up the entry fee—the cost of submitting an application and conducting preliminary studies. Given the uncertainties in future demand, carbon regulation and the price of fossil fuels, exploring the nuclear option makes business sense. Whether to actually build is another question.

One key factor is the price of loans. If a plant runs $5 billion in “overnight” costs and the money is spent over five years, interest on capital during the period of construction—the utility’s version of a home builder’s construction loan—could add hundreds of millions or even billions of dollars. To help, the federal government offered the nuclear industry loan guarantees worth $18.5 billion. It quickly received applications for more than $100 billion in funding.

Another factor is just how long that construction period will be. American builders could base their estimates on reactors built recently in Asia, but no one really knows how a project in Texas or Florida might compare with one in Japan or South Korea. If two or three reactors, such as Wallace’s, could get built in the U.S., the issues would become much clearer. Legislation that provides a predictable price for carbon emissions for the next few decades would also bring clarity.

The country needs a better way to manage nuclear waste as well. The federal government signed contracts with the electric utilities in the early 1980s that promised to take spent nuclear fuel off their hands beginning in 1998. But today, 10 years beyond that deadline, the Energy Department has only applied for a license to build one controversial waste repository, at Yucca Mountain in Nevada. Estimates of the opening date range from 2017 to never. An interim plan, such as long-term storage in aboveground casks in a few areas that are dry and sparsely populated, might be within reach. Many plants around the country have maxed out temporary storage in their spent-fuel pools, forcing them to put waste into huge, dry casks. Filled with inert gas to prevent rust, the casks are moved out to concrete pads surrounded by barbed wire, which look a little like basketball courts at maximum security prisons.

Still, advocates say the reactors are inevitable. At Areva, the company that Wallace’s firm has partnered with, the chief executive, Anne Lauvergeon, scoffs at the idea that there is any other choice. Could coal plants sequester their carbon? “It’s not ready at all,” she says. “You don’t know anything about the cost, and the technology doesn’t exist.” In the meantime, world demand is galloping ahead. Her company will build in China, she points out, and would like to build the first reactors in the Persian Gulf.

In the U.S., many power industry experts doubt that more than a few reactors will be built, at least until company executives see how the first ones go. But potential reactor builders sense that the world has changed enough to consider going back into business, with designs that are optimized and standardized versions of what they built more than 20 years ago. And people like Michael Wallace want to get going while those companies’ engineers still remember how.

http://www.sciam.com/article.cfm?id=can-nuclear-power-compete  

###

October 2, 2008

Indian Point empties leaky fuel pool

By Abby Luby
North County News

The fifth and final canister of spent fuel from Unit I was filled with radioactive spent fuel last week. All five canisters will be stored at the plant.

Workers at the Indian Point Nuclear Power Plant completed a two year project last week, as they finished draining radioactive spent fuel from the plant’s Unit 1 pool.

In 2005, plant owner Entergy discovered that strontium-90, a cancer-causing radioactive isotope, was leaking from Unit 1 and going into the Hudson River. According to Entergy and a 2008 ground water report by the federal oversight agency, the Nuclear Regulatory Commission (NRC), the spent fuel had been leaking since 1990.

Unit 1, the oldest reactor of the three on site, was built in 1962 and closed down in 1974 because of problems in the emergency core cooling system. Groundwater tests in 2005 showed that strontium-90 levels in the groundwater were three times the level allowed in drinking water.

Work to drain the pool was begun two years ago, said Entergy spokesperson Jerry Nappi. “This is significant for us because now all the fuel has been removed,” he said. “There is no more strontium-90 in the pool.” The spent fuel was poured into five canisters which will be stored at the plant. Nappi said that the pool would be completely drained and cleaned by April 2009. “This will completely eliminate the chance for any leakage whatsoever from Unit 1 and close the chapter on this Indian Point legacy issue,” he added.

After all contaminants are filtered out of the pool, the pool is cleaned with high pressure water hoses. NRC spokesperson Neil Sheehan said they were monitoring Entergy’s progress on draining the pool. “The contamination has been there for decades and is the primary source of the most serious contamination at that site,” he said. Sheehan said that the [spent fuel] water is filtered before emptied into storage tanks. “The [chemical] make-up of the water will determine how long it takes for the radioactivity to decay,” he explained. “When it is at a low level it will be slowly released into the Hudson River.” According to the Environmental Protection Agency, it takes 29.1 years for strontium-90 to lose half its radioactivity.

Phillip Museegas of the environmental group Riverkeeper said he was glad to know the pool was drained. Riverkeeper has opposed the operation of Indian Point mainly because of the plant’s impact on the Hudson River. “I think it’s a good development because the source of the leak will be resolved,” he said. “The draining and cleaning of the Unit-1 pool still doesn’t address the contamination that has been leaked out and leached into the Hudson River,” Museegas added. “Our main concern is about the environmental impacts of strontium-90 and if those can be remediated. Although the law allows for the release of radionuclides into the river, we disagree with that. And does [Entergy] really know what’s in this sludge?”

There are 57 wells monitoring ground water for radioactive leaks at Indian Point. Nappi said the monitoring program is still in progress, including the wells around Unit 1.

Siren system update

Entergy ran the second in a series of three tests on their new, emergency notification siren system last month.

“We are pleased to say that we had a 99.4 percent success rate,” said Entergy spokesperson Robyn Bentley of the Sept. 24 tests. “The NRC requires a 97 percent success rate.”

Only one of the 172 sirens failed to sound, located in Stony Point, Rockland County. Entergy sent a crew to check out the faulty siren.

The NRC was monitoring the tests, according to agency spokesperson Neil Sheehan. “We issued a confirmatory order for the testing of the new system that specified the sirens need to work at a high percentage,” he said.

The Federal Emergency Management Agency (FEMA) required Entergy to test the new system for one year before dismantling the old system, a 156-siren system that is still operational. In August, FEMA agreed to have the new system placed in service.

Entergy was mandated by the Energy Policy Act passed in Congress in 2005 to install an emergency alert system with backup power in case of a power black out. The system cost Entergy $30 million and is able to alert some 300,000 residents within 10 miles of the reactors. In the last two years, Entergy has missed two deadlines to replace its old siren system and paid $780,000 in fines to the Nuclear Regulatory Commission.

The new sirens can be heard within the 10-mile Emergency Planning Zone in Westchester, Rockland, Putnam and Orange Counties. A low-level siren sound will be heard in Harriman State Park and Bear Mountain State Park and is reported to have 60-square miles of additional coverage.

Emergency planning booklet

Last week, Westchester County mailed out the latest version of the Indian Point Emergency Planning Guide that helps people know what to do if there is an accident at Indian Point. The guide, “Emergency Planning for the Indian Point Nuclear Plants,” has an updated map listing evacuation routes, reception centers, bus routes and critical information about school relocation centers.

Yorktown residents will have to report to such reception centers as Fox Lane High School in Bedford and H.C. Crittenden Middle School in Armonk. Residents in Peekskill will go to White Plains High School. Cortlandt residents will head to Harrison High School in Armonk.

The guide also tells where to get free KI-potassium iodide if there is a radioactive release. The KI pills prevent thyroid cancer. It also explains that pets are not allowed at receptions centers and advises pet owners to get their pets to kennels or relatives outside the 10 mile emergency planning zone.

###

http://www.northcountynews.com/news/ncn_news4.asp  

September 30, 2008

Nuke agency should expand relicensing rules

Poughkeepsie Journal

Westchester County executives have gone a step further in pushing for reform in nuclear power plant relicensing. That's a wise and necessary move considering there is an aging facility in the densely populated backyard of the Indian Point Nuclear Power Plant in Buchanan.

As Westchester authorities argued in court recently, the Nuclear Regulatory Commission must retool its requirements for extending licenses, making it as rigorous to win an extension as it is to get one in the first place.

The licenses for the two reactors at Indian Point expire in 2013 and 2015, and plant owner Entergy wants to extend those by another 20 years.

The population density and the ability to successfully evacuate during an emergency are not examined in a 20-year license renewal. But they would be reviewed for new reactors in the same location.

Only issues such as managing aging pipes and other infrastructure or possible environmental impacts are considered in relicensing.

The Indian Point relicensing is more than a year under way, and a decision is expected in about two years.

It promises to be a contentious relicensing procedure. The company missed several deadlines to install a long-awaited emergency siren system. Indian Point has had a host of other problems, ranging from leaks of radioactive water that have had to be contained, to failing warning signals and a shoddy evacuation plan.

Several municipalities have passed resolutions demanding the plant be shut, and the region's congressional delegation is pushing for a independent safety assessment of the plant before permits are renewed.

Westchester County officials and New Jersey environmentalists petitioned the Nuclear Regulatory Commission three years ago to expand its criteria and were turned down. They took their case to the U.S. Court of Appeals for the Second Circuit, where they made the recent arguments in New York City.

Among their chief concerns: the Nuclear Regulatory Commission's rejection of their petition was not based on a true evaluation of safety concerns. They also said too much information about this issue was not made available to the public because it fell under the umbrella of "security'' concerns.

According to the petitioners, there were plenty of reports showing how ineffective an evacuation around Indian Point would be in the event of a nuclear accident.

District Judge Robert Katzmann chastised the Nuclear Regulatory Commission's denial of the original petition, saying it was unjust to insulate the agency from judicial scrutiny.

Nuclear Regulatory Commission attorneys countered, saying such things as demographics are examined as part of a new license and other issues such as security and evacuation plans are evaluated in an ongoing manner.

They also said there were a variety of options for members of the public to challenge the operation of a nuclear plant as unsafe or to push for a change in regulations.

That isn't good enough. As Westchester County and the environmental groups are arguing, regulations governing the relicensing of plants such as Indian Point must be comprehensive to begin with and not left up to the whim of a public challenge.

###

September 22, 2008

Indian Pt. neighbors may hear 'gunshots' during drill

By Greg Clary
The Journal News

BUCHANAN - Residents around Indian Point who hear gunshots or other disturbances coming from the nuclear plant this week should not worry - they're only simulated attacks to improve overall security.

The force-on-force exercises, as they're called, will be conducted today through Thursday in unrehearsed scenarios designed to test officers' ability to respond.

"It's likely that residents will hear the activity," said Jerry Nappi, a spokesman for Entergy Nuclear, the company that owns and operates Indian Point. "Even residents of Stony Point have called in the past to inquire because they heard the gunshots."

Nappi said the drills will involve only Indian Point personnel, with no interaction with local or state police.

Nuclear Regulatory Commission officials know of the exercises, but will not be participating. An official NRC-evaluated drill will take place about a year from now, on the three-year cycle the agency employs to test readiness.

"This is basically an in-house scrimmage, a training exercise," said NRC spokesman Neil Sheehan. "They do their own exercises because they need to stay sharp and they need to train for the evaluated exercises."

Company and regulatory officials declined to detail what aspects of security will be tested or how many people are involved. Nappi said the company is bringing in replacements to run the nuclear plants while the regular workers participate in the practice runs.

"This exercise will provide us the opportunity to test our security and defensive capabilities at Indian Point," site Vice President Joe Pollock said. "We will also take feedback and use it to further improve our already robust security program."

During the drills and exercise, people near the site may hear the sound of simulated gunfire or other loud noises as participants carry out scenarios that are intended to be as realistic as possible.

The exercises involve attempts to gain access to plants in a simulated terrorist attack, and the response of defending security forces.

"We are informing the public now about these events so there is no undue alarm caused by what they may hear around the site," Pollock said. "Please do not go to Indian Point unless previously authorized. While we would like to be able to publicly demonstrate our skills and defensive plan, in the interest of maintaining the highest possible level of security, we simply cannot."

The exercises will go on in the evening as well as during the day.

Only people with top federal security clearances will be allowed to observe the exercise. Security experts will analyze the participants' actions at each step of the exercise to determine how responses might be improved or applied to other facilities, the company said in announcing the exercises.

Entergy will be using a technical innovation for the exercise known as MILES gear, or Multiple Integrated Laser Engagement Systems. Participants using the gear are connected wirelessly to a central computer.

The gear includes laser "bullets" and vests with laser-detection equipment, and it duplicates the effects, including the sound, of live ammunition.

The movement and shooting accuracy of the security officers and other exercise data are collected by the computer for analysis. The gear is used for military and counterterrorism training across the country to be as realistic as possible without using real bullets.

###

http://www.lohud.com/apps/pbcs.dll/article?AID=/20080922/NEWS02/809220334/1023/NEWS07  

September 11, 2008

County to fight NRC in federal court

By Abby Luby
North County News

Westchester County is taking the Nuclear Regulatory Commission to federal court, saying its relicensing guidelines for nuclear power plants are inadequate.

For the last three years County Executive Andrew Spano has argued that the NRC criteria for relicensing the 40-year-old Indian Point Nuclear Power Plant fails to protect the public. The county will make that argument in court on Friday.

In a statement released Tuesday Spano said the NRC should use the same criteria for Indian Point that is used to license a new plant.

“In this day and age – and with all the problems Indian Point has had – it is not right to grant a relicense just because it met standards three decades ago,” Spano said. “The health and safety of Westchester residents will only be protected if the NRC is forced to use the broadest criteria possible.”

Entergy, owner of Indian Point, applied for a new license in April, 2007 for reactor units 2 and 3. The licenses expire in 2013 and 2015. A new operating license would extend the plants operation for an additional 20 years.

Westchester County filed a petition to change the relicensing criteria of the NRC in May 2005. The NRC denied the petition in December 2006 and the county filed an appeal in February 2007. The appeal argues that if a new nuclear power reactor were to be built today, it would never be on the Indian Point site.

“If you want to put a new nuclear plant in Westchester County today, federal regulators would have to look at a number factors: population density, emergency escape routes, plant design, and safety and environmental concerns,” Spano said.

This isn’t the first time the NRC has been challenged on relicensing criteria said NRC spokesperson Neil Sheehan.

“In recent years there have been several lawsuits challenging our regulations for license renewal,” he said. “What the federal courts have told the government entities [making the appeal] is that they need to exhaust their remedies with the NRC before they can challenge any of the regulations in federal court.”

The current re-licensing guidelines for nuclear power plants in the Untied States look at the working components and how they are managed in an aging plant. The NRC doesn’t consider local demographics or emergency evacuation plans in the relicensing criteria.

Entergy spokesperson Jim Steets said that the criteria for relicensing have changed since Indian Point was first built in the 1970s.

“The standards have been raised since the plants were first licensed and we’ve had to comply with those standards,” he said. “With respect to emergency planning, the standards have always been the same. We have bi-annual exercises and we maintain a program reviewed by the county, FEMA and the NRC.”

Spano has consistently said that if this were Indian Point’s first license, it would be rejected due to population density and congested road network that would hinder any evacuation plan in a fast-breaking scenario such as in a terrorist attack.

But Steets said Entergy finds the county’s move to change the relicensing guidelines without merit.

“Their appeal to the NRC was and has remained baseless,” he said. “It’s also a waste of the taxpayer’s money.”

Michael Kaplowitz (D-I, Somers) said he hasn’t heard his constituency complain about the cost of the county’s appeal.

“I think people realize the overriding issue here is safety,” Kaplowitz said. “Besides, the county has already paid for the legal work so they might as well see it through.”

Westchester County is represented in the proceedings by the national law firm Epstein Becker & Green, P.C. But County Legislator George Oros (R -Peekskill) contends the move is a waste of money and was only done for publicity.

“It seems as though this is an attempt made for the sake of a PR campaign,” he said. “It’s typical of this administration and always has been.”

Oros also questioned the timing of Spano’s announcement.

“Yesterday our board of legislators unanimously passed a resolution setting a goal to reduce carbon emissions and green house gases,” he said. “At the same time we have people in county government calling for the closure of a plant that probably provides the cleanest energy you can get.”

The federal law governing the NRC is the Atomic Energy Act and any changes in the relicensing criteria would have to be voted on in Congress.

“The Atomic Energy Act, as it is currently written, supports the NRC’s position,” said Kaplowitz. “Any changes to the law would take a new Congress, new laws and a new president to sign it. I don’t think the courts will overrule the NRC.”

Others who have joined Westchester’s appeal are New York State Attorney General Andrew Cuomo, the Connecticut attorney general, the New Jersey Environmental Federation and the New Jersey Chapter of the Sierra Club.

The NRC holds that the relicensing criteria have stood up over time. “We’ve been very consistent on this,” said Sheehan. “The regulations that were developed in the 1990s took years to develop and involved a lot of public input. We look at what’s most crucial to maintain and monitor a plant including potential environmental impacts.”

###

http://www.northcountynews.com/news/ncn_news1.asp  

September 4, 2008

Report says Indian Point, New York area at risk

By Abby Luby
North County News

New research reveals that not one, but two seismic faults run beneath the Indian Point Nuclear Power Plants in Buchanan.

The recent report by Columbia University's Lamont-Doherty Earth Observatory says that a previously unknown seismic zone runs from Stamford, Connecticut to Peekskill, passing less than a mile north of the Indian Point nuclear power plants. The fault line intersects with the Ramapo seismic zone that runs from eastern Pennsylvania to the mid-Hudson Valley, which is within a mile or two northwest of Indian Point.

The main author of the report is Columbia’s Professor Emeritus Dr. Lynn Sykes, a nationally known expert on seismology. Sykes said the findings came from using modern seismic instruments yielding sophisticated analysis on past quakes and 34 years of new data on tremors.

“There is quite a bit of activity around Indian Point, as far down as 10 miles below the surface,” he said. “We recorded small earthquakes less than magnitude 3, which we have in this area about every four years. We had a magnitude 5 earthquake in 1884. Our study shows that the likelihood of a magnitude 5 earthquake is about every 100 years.”

Jim Steets, spokesperson for Entergy, which owns the twin reactors at Indian Point, said the plants were built to withstand a seismic event with a magnitude 7 on the Mercalli Scale.

“That was built into all of the safety related equipment which requires seismic protection,” he said.

The report says that it’s not the magnitude of a possible earthquake under Indian Point, it’s how the resulting seismic gravitational acceleration will make the plant move and shake.

“Indian Point units 2 and 3 were designed for 15 percent gravitational acceleration,” said Sykes. “Our report estimates a 20 percent gravitational acceleration for seismic activity specifically under Indian Point.”

Sykes added that the reactors would shake even if a seismic event was as deep as 10 miles down.

“The information about gravitational acceleration is a big deal,” said Dan Hirsch, president of Committee to Bridge the Gap, a California based group studying that state’s numerous earthquake activity and their affects nuclear power plants. “What you worry about is not so much the magnitude but the gravitational acceleration and how quickly the ground moves where the reactor is,” explained Hirsh. “These reactors are generally designed for low gravitation acceleration, or “g” forces. If indeed the new evidence indicates that the new fault structure can produce ground acceleration significantly higher than this reactor was designed to withstand, it is a potentially very dangerous situation.”

Massive shaking of the reactors could rupture the coolant pipes which would overheat the radioactive fuel causing it to melt (known as a meltdown) and releasing massive quantities of radioactivity to surrounding areas.

Steets said that the plants were designed with what’s known as “snubbers” to protect the reactor against movement after an earthquake.

“These are like large shock absorbers that will buffer against any possible movement,” he said. “Also the plant’s steel re-enforced concrete protects the equipment.”

Hirsch recalled that the twin reactors built in the 1960’s in Diablo Canyon ended up being retrofitted after fault lines were discovered after the plant had already been constructed.

“They spent about $5 billion adding pipe supports and restraints. The rate payers are still paying for it.”

Neil Sheehan of the Nuclear Regulatory Commission, the federal oversight agency for the nuclear industry, said that although the agency already knew about the second fault line, they would be reviewing new seismic report.

“This is really a reinterpretation of information already known to the NRC staff,” he said. “Seismic issues are considered when plants are first built. We don’t take a fresh look at them unless new and significant information comes to light.”

Sheehan also said that the NRC doesn’t revisit seismology issues in the license renewal process. Entergy has applied to the NRC for two new operating licenses for units 2 and 3. The current licenses expire in 2013 and 2015.

Contentions filed against the license renewal because of the fault lines were rejected by the NRC licensing review board, said Sheehan.

Susan Shapiro, a Rockland based attorney who filed contentions against the re-licensing application said the seismic report is just the kind of new information the NRC should consider.

”This is a new, superseding license application and the NRC is being negligent in not considering the new study. It must be considered. They are not following their own regulations.”

A 2001 analysis by the Federal Emergency Management Agency ranks New York the 11th most at-risk U.S. city for earthquake damage. The analysis is based on the state’s history, population density and fragile, interdependent infrastructure.

###

http://www.northcountynews.com/news/ncn_news4.asp  

September 3, 2008

Feds delay decision on license renewal

By Greg Clary
The Journal News

Federal regulators will delay a decision on renewing Indian Point's operating license an additional four months - until late summer 2010 - to give them more time to evaluate safety and environmental issues at the nuclear plant.

"We have said from the beginning that we are committed to a thorough and rigorous review of the Indian Point license renewal application. That has not changed," said Brian Holian, director of the Nuclear Regulatory Commission's Division of License Renewal. "The fact that we will, when necessary, take additional time to address outstanding issues underscores our determination to give this application our full measure of attention."

Staffers at the agency want more time to review additional information provided by the plant's owner, Entergy Nuclear; to respond to a record number of contentions opponents filed against the application; and to address generic issues presented by the agency's Office of Inspector General in a recent report on the NRC's license renewal program.

NRC officials said the "exceptionally high" number of public comments received on environmental questions also played a role in extending the schedule.

Entergy spokesman Jim Steets said the schedule is up to the NRC, and the company would follow whatever time frame the regulators set.

"Entergy appreciates the NRC's thoroughness in ensuring a comprehensive review of the issues and will continue to provide the NRC with the information it needs," Steets said.

Indian Point is seeking to extend its operating licenses for Indian Point 2 to 2033 and for Indian Point 3 to 2035. Indian Point 1 has been closed since 1974 and is not part of the application, which the company submitted in April 2007.

The NRC's standard schedule for a license renewal is 22 to 30 months, depending on whether a hearing is required to review contentions brought by those who oppose the extension or have questions that regulators agree need to be more fully explored.

Indian Point's review schedule was pushed back almost from the beginning as the NRC allowed the company to amend its application and started the clock as of Aug. 1, 2007.

NRC officials said a longer process was "likely" at that point, given the amount of public opposition to the nuclear plant, which first started producing electricity in 1962 and has faced a higher- than-average number of safety and environmental issues almost from the beginning.

Opposition to the plant escalated after the Sept. 11, 2001, terrorist attacks, primarily because one of the planes that hit the World Trade Center flew over Indian Point, and government reports indicated that terrorist leaders had copies of plans for American nuclear plants.

That opposition has produced the largest number of contentions in the NRC's history of license renewal reviews, and the only time a host state has joined in fighting relicensing.

As of now, the NRC expects to have a draft environmental impact report ready by mid-December and a draft safety report by mid-January 2009.

A public meeting on the environmental issues is set for February 2009. No meeting on the safety report has been set.

Under NRC regulations, the original operating license for a commercial nuclear power plant has a term of 40 years. The license can be renewed in 20-year increments if NRC requirements are met.

Additional information concerning license renewal reviews in general and the Indian Point application in particular are available at www.nrc.gov/reactors/operating/licensing/renewal.html .

###

www.nrc.gov/reactors/operating/licensing/renewal.html  

August 28, 2008

DEC says Indian Point affecting aquatic life

By Abby Luby
North County News

State wants new cooling system

In a long-awaited landmark decision, New York State has formally ruled that the water cooling system at the Indian Point Nuclear Power Plants adversely affects aquatic life in the Hudson River and that the system has to be replaced.

For the last 30 years local environmental groups have been appealing to the New York State Department of Environmental Conservation (DEC) to enforce the Clean Water Act by ordering Indian Point to replace its outdated water cooling system. Studies have shown the system has been responsible for killing about 1.2 billion fish a year. That number includes fish eggs, as well as small and large fish.

The water cooling system takes in and flushes out over 2.5 billion gallons of river water daily. Water going inside the plant absorbs the heat of the turbines that produce electricity and then the heated water returns to the river affecting aquatic life.

The DEC ruling signals the first time the state has gone on record saying Indian Point’s current cooling system kills fish. The news pleased environmental groups such as Riverkeeper, Natural Resources Defense Council (NRDC) and Scenic Hudson, who have long argued for a new water cooling system. “We’ve won the argument that the water cooling system has adverse affects,” said Phillip Museegas of Riverkeeper. “That’s a big one for us.”

Hearings will now be held next spring to hear arguments to determine what cooling system is best for Indian Point. Jim Steets, a spokesman for Entergy, which owns Indian Point, said the DEC decision was fair because it allows for the energy company’s input. “The process that was laid out gives us ample opportunity to make our case about the cooling methods which will make the most sense for Indian Point,” he said.

In effect, the DEC ruling said Entergy can no longer argue that its system doesn’t impact fish, said DEC spokesperson Yancy Roy. “The decision means that the state is recommending Indian Point use closed cycle cooling,” Roy said. “But there are other mileposts to be met.” Now both sides can raise questions about feasibility, impacts and alternatives to closed cycle cooling.

Indian Point currently uses a water cooling system known as “once-through” cooling, a relatively inexpensive system that helps generate power efficiently. The down side of once-through cooling is that the system traps larger fish against the intake screens. The smaller fish and larvae are sucked past the screens and into the cooling system. To date, 60 nuclear power plants of the 103 in the United States use once-through cooling systems.

The environmentally friendly “closed-cycle” cooling re-circulates the water in a closed system, substantially reducing the large amount of water needed from the Hudson River. The system also cools the returning water, lessening the effects on aquatic life. The DEC has been extending Indian Point’s Clean Water Act permit using the once-through system since 1981. At that time a deal was made with then owner Con Ed that allowed the utility to operate without installing closed cycle cooling by agreeing not to construct a pump storage facility at Storm King, on the west side of the Hudson River.

Con Ed’s permit expired in 1992 but the DEC continued to issue temporary operating permits. In 2003, the DEC granted another permit stipulating that Entergy, who purchased Indian Point in 2001, install closed cycle cooling. Entergy has been challenging that ruling for the last five years.

Taking years to get a DEC ruling on the negative impacts on aquatic life seemed to be a convoluted process compounded by the industry deregulation of the 1990s, said Warren Reiss, general counsel for Scenic Hudson. “Privately owned utilities were fighting tooth and nail against installing closed cycle cooling,” Reiss said. “These utilities have huge resources and hire hordes of lawyers, engineers and biologists - the best money can buy. If closed cycle cooling costs them tens of millions of dollars to install, they are very happy to spend just $1 million a year on lawyers to avoid that. To date, they have been very successful.”

Entergy has maintained that a new closed cycle cooling system would mean building huge cooling towers similar to the large concrete chimneys at Three Mile Island in Pennsylvania and would be cost prohibitive. “We’ve done a study of cost estimates and the system that would be most appropriate for Indian Point will cost about $1.5 billion,” said Steets. “The towers wouldn’t be quite as big as Three Mile Island, but they would be about 100 feet wide and 150 feet tall. That would triple the footprint of Indian Point.”

Grassroot groups working to shutter Indian Point, such as Westchester Citizens Awareness Network (WESTCAN), have said the large, expensive cooling towers proposed by Entergy are propaganda. “They talk about the costliest and most obtrusive technology available,” said Marilyn Elie, co-founder of WESTCAN. “They say that it’s economically unfeasible when they really have no intention of using such a system. It’s a bait-and-switch tactic geared towards scaring the public.”

Don Jackson, branch chief of Region One for the Nuclear Regulatory Commission (NRC), said there are many different types of cooling systems from which to choose. “It all depends on the needs of the plant,” he said. “Engineers from Indian Point will have to make a business decision on that.” The NRC doesn’t have an opinion on what kind of cooling system is chosen because it doesn’t usually impact the safe, day-to-day operation of the plant, Jackson added.

The Vermont Yankee Nuclear Power Plant on the Connecticut River in Vermont is also owned by Entergy and employs a cooling system with banks of 20 towers that are 70-feet tall. Steets said that millions of dollars have already been spent upgrading the cooling system at Indian Point. The upgraded system now has variable speed pumps that limit the intake of water from the river and a fishery turn-screen that intercepts fish before being brought into the plant. “In the last 15 years, Entergy, and Con Ed have spent over $40 million upgrading the cooling system for units 1 and 2,” Steets said. “So does it really make sense to replace the cooling system that has just a marginal impact? That’s the question that needs to be resolved.”

The DEC spring hearings will resemble a trial setting and will be open to the public. “We are cautiously optimistic that this will result in a final decision requiring Indian Point to implement closed cycle cooling,” said Reiss.

###

http://www.northcountynews.com/news/ncn_news2.asp  

August 14, 2008

Contaminated water found near Indian Point

By Abby Luby
North County News

Trace amounts of Strontium-90, a cancer-causing radioactive isotope, have been found in a well on property next door to the Indian Point Nuclear Power Plants.

Entergy Nuclear, the plant’s owner, has been testing the groundwater for the past three years since finding water laced with radioactive nuclides leaking from the plant’s spent fuel pools. Strontium-90 is a carcinogen that lodges in the bones if ingested.

The Strontium-90 was found in a 50-foot well about 1,500 feet south of the power plant at the neighboring Lafarge factory. The well was originally dug in 2000 and is now part of Entergy’s efforts to monitor groundwater leaks. Jerry Nappi, spokesperson for Entergy, said the Strontium-90 did not come from Indian Point. “We don’t believe the Strontium is from the plant because the elevation of the well is higher than the spent fuel pools and the water which carries the Strontium doesn’t go up-hill,” he said

Phil Museegas of the environmental group Riverkeeper, said they are waiting to see the results of tests being done by the New York State Department of Conservation and the Nuclear Regulatory Commission, the federal oversight agency for nuclear power plants. “I don’t think we could accept what Entergy is saying until we hear from the state and public agencies that are involved,” Museegas said. “We just can’t rely on Entergy and hope the problem will go away.”

Neil Sheehan of the NRC said the amount of Strontium-90 in the well was just above the level of detection. “It’s only a fraction of the EPA’s (Environmental Protection Agency) safe drinking water level,” he said. Test results of water samples are expected in about one month.

Sheehan said they believe the Strontium-90 is from background, or atmospheric radiation, a residual from atomic weapons testing in the 1950s. However, as far back as 1994 levels of background radiation were barely detectable according to a 1994 Annual Report produced by the New York State Department of Health (DOH). The 14-year old report, entitled, “Environmental Radiation in New York State,” said that “levels of fission products from previous atmospheric weapons testing continue to show a slow decrease with time” and that “all measurements show concentrations that are below the minimum detectable levels.”

“If this was background radiation I would think it would be showing up in a lot more wells,” said Museegas. “We need to know what the extent of the contamination is – that’s the question that has not been answered.”

The DOH has been monitoring and testing for background radiation throughout the state since 1982. Although data is still being collected annually, it is no longer being analyzed. The last published report from areas around three of the state’s nuclear power plants, including Indian Point was made in 1994.

Assemblyman Richard Brodsky (D-Greenburgh) said other government reports have stated that there is no safe level for Strontium emissions. “The government standard for Strontium is zero,” he said. “We are now seeking to get the Department of Health to do an analysis of the sources and the health dangers.”

Leaks found from the spent fuel pools have been showing up in the groundwater at the plant since 2005. Entergy and the NRC have determined that the leaks are coming from the spent fuel pools which are used to store highly radioactive, used fuel. The pools are about 45-feet deep and below ground level.

Lori O'Connell of the DEC said in an e-mail that the agency is continuing to participate in the ongoing NRC inspection of the groundwater monitoring at Indian Point. “We will be on-site next week with the NRC as part of that ongoing effort,” she wrote. “This issue will be covered as part of that site visit.”

Entergy’s tests results from samples taken from the LaFarage well are due back in four weeks, according to Nappi. “We test the groundwater every three months,” he said. “There are no plans to dig more test wells in the area because our remediation plan has been in place and we feel the system we have is more than adequate.”

###

http://www.northcountynews.com/news/ncn_news3.asp  

August 14, 2008

Entergy says sirens are ready, set to go

By Abby Luby
North County News

Indian Point awaits FEMA’s approval to implement warning system

The new siren system that can alert 300,000 residents to an emergency at the Indian Point Nuclear Power Plants is ready to go, said plant owner Entergy Nuclear at a meeting Friday. The only delay is being cause by a complete review of the system by the Federal Emergency Management Agency. Michael Beeman, regional administrator of FEMA, said final design documents for the alert system were just received from Entergy Aug. 5. “Our engineers are presently reviewing that documentation,” Beeman said. “This is a rather voluminous amount of material we’re going through.” Beeman said he didn’t know if the review would be finished by Entergy’s proposed completion date of Aug. 14 – the last proposed deadline for the service to be put on line.

In the last two years Entergy has missed two deadlines to replace its 156-siren system and has paid $780,000 in fines to the Nuclear Regulatory Commission. The utility company was mandated by the Energy Policy Act passed in Congress in 2005 to install an emergency alert system with backup power in case of a power black out. The system has to be able to alert residents within 10 miles of the reactors.

The new $30 million system has 172 sirens that can be heard within the 10-mile Emergency Planning Zone in Westchester, Rockland, Putnam and Orange Counties. A low-level siren sound will be heard in Harriman State Park and Bear Mountain State Park, said Entergy. Entergy’s project manager, Tim Garvey, said that the new system will have 60-square-miles of additional coverage. “The population coverage is also greater,” he said. “The system will also be able to automatically verify if the sirens have worked.”

About 2,500 residents in Putnam County that cannot hear the sirens will be given tone- alert Radios by November 2008. The 6-inch box radios cost $60 and will be paid for by Entergy who will also supply AA batteries to residents once a year. “The radios are considered ‘enhancements’ to the alert system,” said Michael Slobodien, Entergy’s director of emergency planning. “They will get a signal from WHUD, the emergency alert radio station that activates emergency signals, to counties in the Hudson Valley.” The tone-alert radios are a new addition to Entergy’s emergency alert system and are currently under review by FEMA.

Westchester County Emergency Services Commissioner Anthony Sutton said the county doesn’t want to rush the review but said the long process is finally coming to an end. Fred Dacimo, vice president for Entergy, said the system was robust. “We believe this system meets and exceeds the requirements of the law,” he said. “It’s clear to us that this system is much better than the existing system so the question is, ‘what are we waiting for?’ We need to get this thing approved and in service.”

Although agreeing that the system was an improvement, Sutton reminded Entergy of its inability to meet deadlines in the last two years.“It’s important that it is put into place once it is verified that it meets the design documents,” he said, “but it’s unfortunate that the push to service hasn’t been demonstrated throughout the entire project.”

Entergy said it could get the system up and running within two days after the FEMA approval. NRC Regional Administrator Sam Collins was handed a letter from Entergy just before the start of Friday’s meeting stating that Entergy still hadn’t received the FEMA review of the new siren system. “It’s going to be a day-by-day process,” said Collins. “The commitment date [for FEMA to complete its review] is not established; there’s some uncertainty there.” The NRC said that it will defer any decisions on future enforcement if the alert system is not operating. NRC spokesman Neil Sheehan, also present at the meeting said, “We’ll step back once they have the new system in operation and decide whether any additional enforcement action is necessary.”

The two NRC fines for Entergy were due to factors within their control, added Sheehan. “Aug.14 is a commitment date but it’s not a deadline per se,” he said. During the public comment, Dave Lochbaum, of the Union of Concerned Scientists, asked the NRC about its approach to enforcing fines for Entergy’s missed deadlines. “Were there lessons learned and could you have done it differently?” he asked. “Might you have done a deeper sanity check to see if what Entergy was proposing was realistic? Could you have acted more aggressively when they missed their deadlines?”

Collins said the NRC did do a self assessment when the first deadline was missed. “But our self assessments are not publicly available,” he said. Lochbaum said that the NRC could have chosen to fine Entergy $130,000 a day. He also said that the NRC Inspector General Hubert Bell just started an inquiry into why the NRC fined Entergy only twice for missing deadlines to complete the sirens.

###

http://www.northcountynews.com/news/ncn_news1.asp  

August 5, 2008

Radioactive material found near plant

By Greg Clary
Gannett News Service

BUCHANAN -- Radioactive strontium 90 has been found in trace amounts in a monitoring well next to Indian Point -- the first time the isotope has been detected in off-site groundwater since workers discovered a spent fuel pool leak three years ago.

The Nuclear Regulatory Commission is expected to speak with county officials and others in an afternoon conference call today with Entergy, so the company could detail the preliminary test results it found during routine well sampling on the property, according to NRC documents obtained by The (Westchester) Journal News.

Entergy Nuclear, which owns and operates Indian Point, has been working to stop spent fuel pool leaks that have sent water containing strontium 90 and tritium into the Hudson River.

The test results show strontium levels that are less than 1/16th of federal allowable limits for drinking water, the well tested was not for drinking water.

NRC officials said it was the first time since the leaks showed up in 2005 on the Indian Point property that strontium 90 had showed up in off-site wells.

According to the documents, Entergy officials believe the sample showed the traces of strontium 90 because the most recent test are conducted with a more sensitive analysis, not because of increased levels of radioactivity.

NRC officials said they are fast-tracking a portion of the sample that they took during the test, to check the results as quickly as possible.

###

http://www.northcountynews.com/news/ncn_news3.asp  

July 10, 2008

Indian Point asks NRC for exemption

By Abby Luby  

Wants window to check viability of back up pump system  

Entergy Nuclear has asked the Nuclear Regulatory Commission to drop a requirement that would ensure that a backup safety system at the Indian Point Nuclear Power Plants are working in the wake of a catastrophic incident.  

Entergy has asked the NRC—which is currently considering relicensing the plant—to allow the plant 24 hours to see if the primary emergency system breaks down before ensuring the backup will work.  

According to David Lochbaum of the Union of Concerned Scientists, who wrote the letter to the NRC that strongly objected to the proposed change, the first 24 hours are when emergency components are most likely to malfunction.  

“The piping from the primary pumps is stressed most during the first 24 hours of an accident because of higher water temperature and higher flow rates and that’s when the piping would most likely fail to function,” he said. “Entergy wants their license rules to negate the scenario of failed piping until after 24 hours. It's fanciful for Entergy to solve its problem by hand-waving away a failure at a time when it is most likely to happen.”  

Jim Steets, Entergy spokesperson, said that the exemption is a very small part of a much larger, comprehensive modification of the sump system done to prevent clogging and to ensure water is recirculated for cooling in a major loss of coolant event that has never happened before and which chances are extremely small.  

“Having the exemption does not reduce our capability to operate the sumps effectively,” said Steets. He said that as a result of the modifications made in 2004, the primary sump is much larger and capable of handling debris.  

The nuclear reactor core of a nuclear power plant is housed in its dome, where large pipes pump water in to cool off the reactor. If one of those pipes were ruptured, it would drain cooling water from the reactor and could lead to the core’s meltdown, which would release radiation and could cause millions of deaths as far as 500 miles from the plant, according to a February 2001 NRC report. In order to prevent such an event, the plant is equipped with a primary sump and a backup sump. The backup sump is necessary because, amongst other things, the primary sump could become clogged with debris.  

Entergy’s request was revealed at the NRC’s annual safety assessment meeting last week when a letter from the Union of Concerned Scientists that strongly objected to the proposed change was brought to the attention of NRC regional director Sam Collins. Collins said he was not familiar with Entergy’s request and he referred questions to John Boska, NRC senior project manager. Boska said that Entergy made the request in March and that the NRC now must write a safety evaluation on whether it meets the regulations and the requirements for such an amendment.  

The primary emergency pumps are programmed to respond to pipe breaks by pumping out large volumes of water of about 10,000 gallons per minute. In a worst case scenario, a failure in the primary pump could cause the backup pump to be overwhelmed and fail.

In the event of a large pipe rupture, the velocity of water could scour paint off the walls, rip insulation from piping and tear coating off equipment. The debris would fall to the basement and most likely clog the screens in front of the backup sump. Water needed immediately from emergency pumps to cool the reactor may not be available because of the clog.  

According to Steets, that is why the company spent millions on modifications. According to Boska, many pressurized water reactors such as Indian Point have the 24 hour grace period. “Indian Point is asking to relax their conservative licensing basis to something that’s more in line with what most other water pressure reactors have in the U.S,” he said.  

Entergy, however, is basing that request on an NRC regulation from 1977 that assumed only 50 percent of the sump screens would be clogged from a ruptured pipe. The 24 hour grace period established in 1977 gives plants that period of time to see if enough debris has blocked the pumps from working before checking the secondary system.  

From tests and real events, the Union of Concerned Scientists claims that loosened debris clogs the screens more than 50 percent and based on that, other power plants have made modifications to the screens.  

In 2004, the NRC suggested all plants modify their sumps.  

Losing focus  

At the NRC meeting last week formally assessing Entergy’s safety performance for 2007, some criticized the 24-hour request as another indication of what they called Entergy’s lack of focus on root causes for problems at the plant. NRC panel members criticized Entergy for being much too focused on individual plant components and not looking at the bigger picture of problems at the plants. Pat Conroy of Entergy admitted that the company improperly assessed the NRC findings on staff performance.  

“We couldn’t determine what areas to focus on to address where the real problems are,” he said. “There was slow progress in developing the project with human performance for following correct procedures.”  

NRC’s Mel Gray, chief of projects, reminded Entergy that it had been notified three times about performance by plant workers who didn’t follow procedures adequately.  

“We want to know why you have not yet been successful in clearing this issue,” he said.  

Entergy’s site vice president Joseph Pollack said the company didn’t look broadly enough at the NRC findings.  

“We looked at it in a very myopic way,” he said. “That’s why our process was too slow.”

###

http://www.northcou ntynews.com/ news/ncn_ news5.asp

June 19, 2008

Indian Point licensing board needs more time

By Abby Luby

The Atomic Safety and Licensing Board needs more time to consider arguments that have been made against the re-licensing of the Indian Point Nuclear Power Plants.

The deadline for the ASLB panel to rule on hearings for opposing organizations was June 16, the same day the panel issued a request for more time. According to the Nuclear Regulatory Commission, the federal oversight agency that issues new operating licenses to power plants, the ASLB's deadline was extended to July 30.

NRC spokesperson Neil Sheehan said the panel had more than 150 contentions to consider.

"There have been motions and additional filings for the panel to sort though," he said. "It's not surprising that they are seeking the additional time."

Entergy Nuclear, the owner of the Indian Point plants, applied last year to extend their license to run the Buchanan based reactors until 2033 and 2035. The 2,500 page application was filed last April, launching a two-year process. Sheehan said that the only other license application that is as active as the one for Indian Point is the Yucca Mountain Repository, the Nevada site poised to store spent radioactive waste from the nation's nuclear power plants.

The ASLB panel determines if contentions filed by opposing organizations pose reasonable arguments against the continuing operation of the plant. If the panel rules in favor of certain arguments, the organizations are allowed to be heard in the formal license proceedings.

Among the organizations filing contentions in the fall of 2007 were Westchester County, the New York Attorney General's Office, Riverkeeper, Clearwater, Sierra Club, WestCAN, Rockland County Conservation, Connecticut Residents Opposed to Relicensing of Indian Point, Connecticut Attorney General's Office, and the Town of Cortlandt, Village of Buchanan, PHASE, New York City Economic Development Corp, NY AREA and FUSE. Each series of contentions filed were several thousand pages that needed to conform to specific NRC formatting. The contentions required in-depth legal preparation as well.

Marilyn Elie of WestCan, a local group seeking to close the plant and who submitted contentions, said the filing was expensive and time consuming for grass roots groups. She criticized the NRC for allowing the panel extra time.

"We have jumped through hoops and worked long hours to meet NRC deadlines that were unfair and unchangeable, " she said. "Giving the panel extra time is a prime example of how they change the rules whenever it suits them. The outcome is predictable. The agency is doing everything it can to re-license the plant."

Entergy spokesperson Jerry Nappi said, "We look forward to the Licensing Board panel completing their thorough and comprehensive review as we make our case for the continued safe operation of the two plants before the ASLB, and ultimately license approval."

The NRC said that the re-licensing process only looks at how the utility company manages the interior components of an aging plant with attention given to age-related structural degradation of plant components like reactor cores, containment systems, pipes and electrical cables. Contentions filed have criticized the process for omitting any possibility for catastrophe including the plants location in a densely populated area, susceptibility to terrorist attacks, an inadequate evacuation plan and seismic issues.

###

June 13, 2008                                                                                                

Contrary to claims, power plants do slaughter fish
Journal News Community View

 By Alex Matthiessen , Hudson Riverkeeper and president of the organization

The "In Reply'' piece by Jim Steets, communications manager of Entergy Nuclear ("Nuclear plant not to blame for shad decline in Hudson ,'' June 7) that was in response to your editorial ("Missing in action: A 'chicken-or- egg' riddle for the Hudson deserves real inquiry,'' May 20) is riddled with slippery logic and false statements.

Steets contends that the New York State Department of Environmental Conservation found that Indian Point has had "no appreciable influence on the Hudson River American shad." In fact, the DEC's May 2008 plan for the recovery of Hudson River American shad states that young shad are lost to the cooling water intake structures of power plants. Moreover, one of the agency's three primary strategies to reduce the mortality of shad is to "reduce or eliminate losses of all shad life stages to Hudson River power generating plants."

Steets' focus on shad cleverly diverts attention from the overall results of the report conducted by Pisces Conservation Ltd., which implicated Indian Point and other Hudson River power plants as significant contributors to the decline of Hudson River fish. His statement that fish are protected by a fish-return system designed by experts for Riverkeeper is patently false. It is true that former Riverkeeper board member and scientist Ian Fletcher advised Consolidated Edison, Indian Point's previous owner, on a so-called "fish return" mechanism. Unfortunately, the fish return strategy didn't work, and Indian Point's cooling system falls far short of meeting the Clean Water Act requirement that such plants use the "best technology available to minimize environmental impacts." As Gov. David Paterson said in a May 28 press statement, the majority of 1.2 billion fish eggs and larvae, and 1.18 million fish that come into contact with Indian Point's antiquated cooling system each year, likely die.

Steets' charge that the Pisces study contradicts information on Riverkeeper' s Web site about an increase in striped bass is false and disingenuous. Of 13 species examined by the report, striped bass were one of only three that are increasing in number. This is attributable to particular circumstantial changes that happen to favor them - for example, the closure of the commercial striped bass fishery due to PCB contamination, as well as size limit restrictions on the recreational fishery.

Steets' reference to the analysis of scientific data collected over several decades that has "shown no negative impact on any Hudson River fish" was conducted by the power plant operators themselves - hardly a reliable source given their financial incentive to play down the impacts of their cooling systems on the river's aquatic life. In fact, the report's findings are supported by the data and by biologists from the DEC Fisheries unit, and do nothing more than confirm the link between power plants and fishkills established long ago by the DEC and independent scientists.

The Pisces study was designed to analyze the power plant operators' data and determine long-term trends for the 13 species studied, as required by the DEC. Given the clear downward trends for most of these fish, the next step is for the DEC to conduct a more in-depth analysis to determine what role various factors - climate change, overfishing, sewage, habitat loss, invasive species and power plants - are playing in the decline of each of these fish. However, we currently know enough to definitively link Indian Point and other power plants with some of these declines. Each year, we know that virtually 100 percent of the 13,380,000 shad, 326,666,667 bay anchovy, 466,666,667 river herring, 158,000,000 striped bass and 243,333,333 white perch entrained in Indian Point's cooling system die. If 95 percent of these fish had avoided being destroyed by Indian Point's intakes, as they would have were the plant equipped with the "best technology available," the river's fish populations would certainly be stronger than they are today.

It is way past time for Entergy and the other out-of-state power plant operators to stop slaughtering our fish. And if Entergy is truly committed to being a "good neighbor,'' the company should invest in upgrading its Indian Point facility to meet the clear requirements of the Clean Water Act, rather than in a well-funded campaign to blanket the Hudson Valley with misleading and dishonest propaganda.

###

June 2, 2008

100 tons of dreck cleaned out of pipes

Greg Clary
The Journal News

BUCHANAN - Tucked into a recently released report on radioactive contamination at Indian Point is a note from federal regulators about more than 100 tons of debris that power plant workers found built up in the storm-water system since the 1950s.

The underground pipes - 3 feet wide in some cases - are not connected to the radioactive operation at the nuclear plant but were examined as part of the investigation into tritium and strontium 90 leaks at the plant.

Hydrologists working for plant owner Entergy Nuclear wanted to make sure storm water wasn't influencing the movement of radiated water underground.

Company officials said monitoring wells dug at the site turned up little evidence of storm water reaching contaminated areas.

John White, the Nuclear Regulatory Commission official in charge of the groundwater inspection, said the amount of debris was significant, and that the company had cleaned out the pipes by the fall of last year.

The NRC included the information in the 56-page report to make the document as comprehensive as possible, agency officials said.

It appears the storm-water pipes have not affected the movement of radiation, White said.

"They never did any extensive maintenance repair of the system over time," he said. "Now they have a maintenance program in place."

Donald Mayer, the Indian Point official in charge of the groundwater contamination project, explained that workers found the debris by running cameras into the pipes and vacuuming out the sediment before it was disposed of as radioactive waste.

"We just wanted to be on the safe side," he said. "We did some repairs, but they were relatively minor. Cleaning the debris out was quite an effort."

Mayer didn't have an exact cost of the cleanup, but he estimated it was "hundreds of thousands of dollars."

Underground piping at Indian Point has gained in profile in the past two years as Entergy officials exercised their right to apply for 20-year license renewals for the two working nuclear reactors at the 50-acre site.

Critics of the company have presented arguments to the NRC against the relicensing, highlighting the difficulty in determining whether buried piping that carries radioactive water under high pressure can be adequately maintained through 2035.

Company officials will have to prove to the NRC that they have adequate plans to manage the aging infrastructure to be granted an extension. Though the storm-water system is different than the piping system that serves the reactors, Mayer and White said the overall robust condition of the rain runoff pipes was a positive sign.

"There were no significant stoppages or problems," White said, adding that sampling of water being released into the Hudson River showed strontium or tritium levels had not changed after the debris was removed.

###

June 1, 2008

The Journal News

Mock drill not enough to ensure safety

On May, 22, Entergy and Phelps Memorial Hospital conducted a mock drill to treat a supposedly radioactively contaminated Indian Point worker. Entergy and the hospital are to be commended for practicing for an event that can occur when working with a nuclear power plant.

However, what type of drills are conducted to practice for a major release event, and how would any hospital be able to handle it? We know that accidents can happen. That is why every nuclear plant has to have an evacuation plan. According to the report in this newspaper, 65 members of the staff were trained to respond to radiation exposure victims, and 22 of those medical professionals, one-third of the trained staff, were involved in treating the single victim in this drill. What would have happened if 10 workers were exposed simultaneously, or if there were the type of event that required evacuation and only 50 local residents were exposed, but many more run to the hospitals because they think they might have been exposed?

The point is, in the event of a large release, all medical facilities will be overwhelmed and, as the Witt Report pointed out, the evacuation plan is doomed to fail. That is why the Nuclear Regulatory Commission now discusses sheltering in place as its solution. Are these the types of risks that we want to live with for another 25 years if the plants are relicensed? I, for one, do not want that.

Mary Cronin

Croton-on-Hudson

###

NRC: Indian Point's handling of leak followed procedure

By Greg Clary
The Journal News • May 21, 2008

CORTLANDT - Federal regulators have approved Indian Point's handling of radiation leaks first discovered at the Buchanan plant in August 2005, telling the public last night that the company followed procedures and protected residents, even though strontium 90 and tritium are likely still reaching the Hudson River.

The Nuclear Regulatory Commission's findings allow Indian Point's owner, Entergy Nuclear, to leave the ground contaminated with an estimated swimming pool's worth of radiated water until the reactors no longer are licensed to operate.

At that point - between five and 25 years from now - the company would have to dig out the contaminated ground and dispose of it as hazardous material.

Opponents derided the decision after a 75-minute presentation by Entergy and the NRC, saying the NRC should be requiring a more immediate cleanup rather than allowing it to sit in the ground.

Workers first discovered a tritium leak nearly three years ago, and the efforts to determine the extent of that leak led them to find a strontium 90 leak more than two years ago.

NRC, Entergy and state public health officials have maintained since the discovery that the level of radioactive material making its way into the environment and into humans was well below what is present in nature or everyday life.

"This is a challenging technical issue," Marc Dapas of the NRC told a crowd of about 50 people gathered at a catering hall in Cortlandt for the presentation. "We do think we've provided you our reasons. It is important for us to continue to monitor the situation."

Dapas, the second-highest-ranking agency official in the region, said the entire volume of leaked radiated water from Indian Point 2 and Indian Point 1 is on the order of 20,000 gallons.

Some media reports had the volume estimates closer to 1 billion gallons, about the same size as the Central Park Reservoir. Dapas said those estimates were way off.

The NRC's report on the groundwater contamination, which the agency considers a status update rather than the final word, noted only one minor problem with Entergy's efforts to control the leak: one set of monitoring well data was mishandled by the company's laboratory and led to that lab being replaced.

Opponents of the plant sounded as if they wanted the NRC replaced.

"The overall plan here, which they're calling 'monitored natural attenuation,' simply means, 'We're done. Let nature clean the rest.'  That's not acceptable," said Mark Jacobs, a longtime member of Indian Point Safe Energy Coalition.

Philip Musegaas, a policy analyst with the environmental group Riverkeeper, said his organization would continue to push for a quicker cleanup, to protect the river and lower the chance that the leaks could end up pushing more radiation to the Hudson than can be monitored by wells.

Musegaas also raised concerns about whether Entergy or whoever owns the plant at the time of its decommissioning and subsequent cleanup would have adequate money to do the job properly.

Dapas said there was no reason to require that additional money be put aside for the cleanup because the owner would have to take care of all its responsibilities before the NRC would sign off on the closing plan.

Indian Point is seeking 20-year extensions to its current operating licenses for Indian Point 2 and 3, which would allow the company to produce electricity from uranium until 2035. Indian Point 1 has been closed since 1974.

Entergy officials said emptying the spent fuel pool of its contents - which will be stored in dry casks containing helium - should take away the source of strontium 90 by the end of 2008.

The tritium leak is down from 1.5 liters a day to "a couple of tablespoons," according to Donald Mayer, the Entergy official heading up the groundwater contamination project.

###

Entergy nuclear spinoff plan meets resistance in NY

By RICHARD RICHTMYER | Associated Press Writer
http://hosted. ap.org/dynamic/ stories/N/ NY_ENTERGY_ SPINOFF_BAOL- ?SITE=WPIX&SECTION=NORTHEAST&TEMPLATE=DEFAULT
May 20, 2008

ALBANY, N.Y. - Entergy Corp.'s plan to spin off its northeastern nuclear division into a standalone company has hit a snag in New York.

Lawyers for Entergy _ which owns three nuclear plants in New York _ want state utility regulators to endorse the plan, which they say will be good for consumers because it will provide the company with more financial flexibility.

Opponents say the plan would enrich Entergy and its stockholders at the expense of New York consumers while allowing the company to avoid responsibility and liability for the plants.

The New York Public Service Commission, which oversees utilities in the state, is expected to consider the plan at its meeting Wednesday, said commission spokesman James Denn.
New Orleans-based Entergy wants to separate five of its nuclear plants that sell electricity on the open market into a standalone company. Entergy would keep a 50 percent stake in the new company, while the other half would go to its shareholders.

The spinoff would include two plants at the Indian Point station on the banks of the Hudson River in Westchester County as well Oswego County's James FitzPatrick plant. The two other plants are Vermont Yankee in Vernon, Vt., and the Pilgrim plant in Plymouth, Mass.

New York's attorney general _ who is also opposing re-licensing the Indian Point plants _ and Westchester County officials have asked the Public Service Commission to reject the plan.

In a 156-page objection, Attorney General Andrew Cuomo's office tells the Public Service Commission that the state is concerned that the spinoff _ which includes the new company borrowing up to $6.5 billion _ would significantly reduce the financial resources currently available to support the plants, which would rely on funds from riskier sources.

The attorney general also argues that the spinoff would enable Entergy to avoid paying up to $360 million to the New York Power Authority.

The Power Authority _ a state agency that sells power without profit _ sold one of the Indian Point plants as well as the FitzPatrick plant to Entergy in 2001. Entergy agreed to pay the authority up to $72 million a year until 2014 as part of that sale.

The attorney general's office notes that in Entergy's annual report for 2007, the company points out that a clause in that agreement terminates the payments if Entergy or an Entergy affiliate ceases to own the plants.

"Entergy predicts the reorganization will enable Entergy to disclaim ownership of Indian Point 3 and FitzPatrick in 2008 and thus get out of paying NYPA beyond the installment due in January 2009," the attorney general's filing says.

Westchester County Executive Andrew Spano is also trying to block the spinoff, which his office says would result in a complicated set of subsidiary companies that would throw into question who is responsible for the plants.

Stewart Glass, a senior assistant county attorney who is working on the issue, said the county is particularly concerned about what will happen when it comes time to decommission the plants.

"We're worried that Entergy or its successor corporation will not live up to its responsibilities to the local communities and the local communities will be left to solve all the problems in the future," he said.

Entergy executives did not return phone calls seeking comment.

In a 237-page written response to opponents' objections, the company said they "provide no legitimate basis" to reject the plan or require a more thorough review.

###

http://www.northcou ntynews.com/ news/ncn_ news4.asp  

May 1, 2008  

Entergy safety panel holds first public sessions

 By Abby Luby

The special panel of experts hired by Entergy to assess safety at its Indian Point nuclear plants held two public sessions on Monday to get feedback on the reactors.

Eleven of the 12 panelists, all specialists in the nuclear industry field, heard questions and comments from people both supporting and opposing the operation of the plant.
There was sparse attendance at the first meeting, which was preceded by a press conference held by New York State labor leaders.

“I’m here speaking on behalf of 2.5 million men and women of labor in New York State and to tell the Independent Safety Evaluation panel that we support the continued operation of this safe, secure and necessary power plant,” said Jerry Connolly, a retired business manager and board member of Boilermakers Local 5 New York. “We want to make sure that all of the safety concerns are being addressed.”

About 100 people attended the second meeting, with many plant workers and union members present. The meeting was boycotted by IPSEC (Indian Point Safe Energy Coalition), a group opposing the plant’s operation. They claimed that since Entergy was paying the panel, the study would be a conflict of interest and not truly independent.

One IPSEC member that didn’t boycott the meeting was Gary Shaw. “It is somewhat peculiar that the NRC and Entergy would oppose the independent safety assessment [legislation] proposed in Congress and then hire their own Independent Safety Evaluation Panel,” he said.
Others praised the panel for their experience in the industry. Craig Upshaw, a member of Local 740, countered Shaw’s skepticism.

“Many on the panel are former naval officers and they have very high integrity,” he said. “It doesn’t matter who is paying for the board, but if anyone doesn’t like it why don’t they pony up and get a panel of their own.”

Legislation was introduced two years ago requiring an independent safety assessment as part of Entergy’s re-licensing process in both the House and the Senate. To date, the bill is still in committee.

After an independent assessment was conducted at the Maine Yankee plant in Wiscasset, Maine, the plant shut down in 1997. The safety assessment team included nuclear experts of the NRC (Nuclear Regulatory Commission), officials of the Maine state government and non-governmental nuclear experts.

Manna Jo Green, the environmental director of Clearwater, urged the panel to resign en masse.

“Public policy would require a true independent safety analysis and I don’t think this is,” she said. “So I request that all of you consider resigning and to preserve your integrity, call on Congress to amend the Atomic Energy Act and create a truly independent safety analysis for Indian Point and all nuclear power plants.”

The Raging Grannies, a group of older women that frequently serenade the public against Indian Point, sang two songs urging to close the plant.

Local volunteer firefighter Tom Johnson praised safety features at Indian Point.
“I’ve worked with the folks at the plant and I am always inspired by their hazmat (hazardous materials) and evacuation capabilities,” he said.

Eliot Sumers, a medical radiologist of Montrose who lives within sight of Indian Point, said he wanted panel members to itemize in their report their connections to the nuclear industry.
“I think it’s appropriate to establish bona fide proof to enter into the record all of your current financial ties to the nuclear industry,” he said. “That should include pensions and stocks from nuclear-related companies and other contracting work you have done.”

Sumers told the panel that although an accident or meltdown is highly unlikely, if it did happen, their names will be on the report claiming the plant was safe.

“You will possibly be remembered in the 21st century as the people who told us this was a safe plant or that it isn’t,” he said. “I ask you to do the job with all the diligence that you have.”
Plant workers said safety rules were stringent. Scott Tadesco, a Peekskill resident and a welder that just worked during Indian Point’s re-fueling said he was speaking for members in his union, local 740.

“I’ve worked at a dozen nuclear power plants and Indian Point is one of the most difficult to be admitted to for work,” said Tadesco. “I had to take two tests to even get inside to solder pipes. They have very serious criteria I see that is imposed on workers at Indian Point.”

Other comments offered more technical information about the plant that could affect safety.
Karl Jacobs, a Cortlandt Manor resident and a senior nuclear operator engineer who worked at Indian Point when it was owned by Con Ed, said there were serious problems with cracks in the pressure vessel at the plant (reactor pressure vessels contain the nuclear fuel and are made of thick steel plates that are welded together).

“There’s cracking going on in the pressure vessel head that Entergy has neglected to take care of,” said Jacobs. “Right now Entergy has elected not to replace this head, which they make clear in their current license renewal application. Their approach or lack of approach is very unusual because it’s a current licensing issue. The cracks are as much as a half inch, which is a big size for this area.”

Margo Schepart of Westchester Citizens Awareness Network, an organization seeking to shutter the plant, asked the panel how it would measure the viability and condition of inaccessible pipes and welds “that have been carrying corrosive Hudson River water for decades.” Schepart went on to say, “The current metric is simply drilling test wells which can do nothing other than let the company and the NRC know when a breach has already occurred. What metric will the panel suggest for preempting future breaches?”

At the meeting’s end, the panel’s co chair, Dr. James Rhodes, said the panel will review comments. “Now we will begin our work,” he said. “Once the evaluation is complete, we will issue our report to the NRC, Entergy, public officials and the general public.”
Rhodes added that there was information he wasn’t familiar with.

“We’ve heard new material about the integrity of the reactor vessels,” he said. “We will certainly look at that.”

###

Appearance is everything

North County News Editorial, May 1, 2008

Remember when you were a little kid and your mom would fawn over you before
you left the house; making sure your hair was combed, you had on a clean
shirt and there were no holes in your socks?

You may have hated it, but Mom knew what she was doing. She knew that how
you appeared to the world was important. She may have known deep down that
her little kid was a slob at heart, but she wasn’t about to let anyone find
out. Keeping up appearances was important to her.

Appearance is everything. Just ask those that run Major League Baseball. In
1919, it endured a major scandal when the Chicago White Sox were caught
throwing the World Series after being paid off by gamblers. MLB banned
eight White Sox players from the game for life and established a rule that
anyone even associating with known gamblers would face the same
castigation. And they were serious. Just ask Pete Rose.

The problem MLB officials were facing was appearances. They knew that if
the integrity of their game was to remain intact, they needed to maintain a
zero tolerance policy when it came to gambling. There could not even be an
appearance of impropriety (games being thrown) because even the slightest
amount of suspicion from the fans would ruin the sport forever.
This is a concept that the Nuclear Regulatory Commission and, by extension,
Entergy, does not seem to understand.

As part of a safety review, the NRC asked Entergy, owners of the Indian
Point Nuclear Facility, to form an “independent” panel of industry experts
to perform the review of the plant. While it’s not exactly like having the
fox guard the henhouse, it’s not far off.

It’s a matter of credibility. Entergy hand selected each panelist and will
compensate them for their work. If this isn’t a conflict of interest, then
that concept doesn’t even exist. Most logical people would wonder, and
rightly so, if these panelists would be willing to bite the hand that is
feeding them.

Again, it all comes down to appearances. The panel that Entergy has
assembled is certainly an august body, a veritable who’s who in the nuclear
energy industry. We have no evidence that any member is or has engaged in
unethical behavior regarding this issue. But because of how this panel was
put together, there will always be the perception that something untoward
is afoot. Once there is an appearance of impropriety, then anything the
panel says or does will automatically be tainted with suspicion.

In fact, before the panel could even take its first, tentative steps this
week, people were already calling for its dissolution.

Manna Jo Green, the environmental director of Clearwater, told the panel
this: “Public policy would require a true independent safety analysis and I
don’t think this is, so I request that all of you consider resigning to
preserve your integrity.”

In other words, just by serving on the panel, says Green, these individuals
are risking their integrity.

The critics may be wrong. The panel may conduct itself with the utmost
integrity and do a thorough, unbiased safety assessment. But because so
much doubt lingers, we will truly never know. We need to be able to embrace
the veracity of their findings, or the panel is moot before it even begins.

Consequently, the NRC and Entergy need to go back to square one and take
the necessary steps to put together a truly independent panel that the
public can believe in.

It’s all about appearances. Just ask Mom.

###

Press Release

Indian Point Independent Safety Evaluation Panel to Hold Public Meeting Monday, April 28, 2008
Wednesday April 16, 11:00 am ET

BUCHANAN, N.Y., April 16 /PRNewswire/ -- The panel conducting the Independent Safety Evaluation (ISE) of the Indian Point Energy Center (IPEC) announced today that it will hold a public meeting later this month. The panel has been asked to look into the nuclear safety, security and emergency preparedness at IPEC and is interested in learning which questions the public would like answered about operations at the facility.

Members of the public interested in the ISE and who would like to speak at the event are encouraged to pre-register by emailing the panel at safety@nyindianpoint.org. Those who may be unable to attend the meeting are also encouraged to submit comments, questions and suggested evaluation criteria to the panel via email.

    Who:   The panel conducting the Independent Safety Evaluation at the
           Indian Point Energy Center.

    What:  Meeting with members of the public to solicit questions, as well as
           suggestions on the scope and specifics of the evaluation.

    When:  Monday, April 28, 2008 in two sessions (2 p.m. to 4 p.m. and 7 p.m.
           to 9 p.m.).

    Where: Cortlandt Colonial Reception Hall, 714 Albany Post Road, Cortlandt
           Manor, NY 10567.

###

Indian Point on the Potomac: Entergy's New Safety Panel and PR Firm

Submitted by Diane Farsetta on Wed, 04/02/2008 - 09:50.

Entergy's Indian Point nuclear power plant

There's no question that New York's Indian Point nuclear power plant could use some public relations help. But Entergy, Indian Point's owner, might have chosen their new PR firm a little more carefully.

Last year, the state of New York asked the U.S. Nuclear Regulatory Commission (NRC) to deny the plant's license extension application, citing "a long and troubling history of problems." It was "the first time that a state had stepped forward to flatly oppose license renewals," according to the New York Times.

Then, in January, the NRC proposed a $650,000 fine against Indian Point, for having repeatedly missed deadlines to install a new emergency siren system. The fine is "10 times the normal size" of such sanctions, reported the Times.

To address such criticisms, Entergy has retained the Burson-Marsteller firm, funded the pro-nuclear "New York Affordable Reliable Electricity Alliance" and brought Greenpeace activist-turned-PR consultant Patrick Moore to